Deer Park High School

Schools Top Projects

Text size: A A

The modernization of Deer Park High School includes 81,000 sq ft of renovated space and 68,000 sq ft of new addition for a total of 149,000 sq ft in the completed project. Site design includes expanded parking for all users and a bus loop that surrounds the school and also provides access for emergency and delivery vehicles.

----- Advertising -----
Key Players

Project Name: Deer Park High School
Location: Deer Park, Wash.
Total Construction Cost: $34 million
Construction Start Date: September 2008
Expected Completion Date: Fall 2010
Owner/Developer: Deer Park School District
General Contractor: Garco Construction
Design Firm (Architect or Lead Engineer): NAC|Architecture
Engineers or Other Design Consultants: Mechanical: SMK; Plumbing: 3-V; Electrical: Pick Electric
Subcontractor(s): Fire Protection: FP Engineering; Landscape:
Gavin Associates; Mechanical Engineering; Meulink
Engineering, Inc.; Electrical Engineering: NAC|Engineering;
Structural Engineering: Structural Design Northwest; Civil
Engineering: Taylor Engineering, Inc

 

----- Advertising -----
Dodge Reports

Below is a brief listing of Projects Bidding in the Alaska, Oregon and Washington. Click on any project to get Dodge Report, Plans and Specifications.

Click Here to See More Projects in the Alaska, Oregon and Washington

Blog: Evergreen
Tim Newcomb is a newspaper and magazine journalist based in Western Washington, covering design and construction in buildings and transportation around the Northwest.
Reader Photos
Photos from Northwest Construction Photo Showcase
----- Advertising -----
Reader Comments: