|
Top Projects of 2003
Could it be that Things are Looking Up?
Just last year, it seemed as though every
breakfast meeting, every construction industry forecast, every
industry seminar bemoaned the state of the commercial building
industry. Business was as bad as it had been in a long time,
and the industry yearned for the 1990s, when tower cranes
rose from nearly every street corner.
Well, we're not quite back to the good old days, but we're
not hearing as much bad news from the A/E/C industry. Could
it be that you're too busy working on new projects?
Project starts in 2003 in Oregon and Washington aren't just
plentiful, they're pretty big as well. Much is happening on
the Oregon Health and Science University campus in Portland
- combined, the construction costs of the Patient Care Facility
and the Biomedical Research Facility total $189 million. Portland
powerhouses Hoffman Construction and Andersen Construction
joined forces to tackle these two mammoth projects.
In Washington, Turner is busy building the $95 million Safeway
Distribution Center, and Absher crews are hard at work on
the 65 million High Point Redevelopment.
The list includes project starts in 2003 ranked by construction
cost. We compiled our data by surveying local contractors
and consulted McGraw-Hill Construction Network for additional
project information. Once we had a firm list of Top Projects,
we looked to the design and construction teams for detailed
information and images.
Know of a Top Project breaking ground in 2004? Watch for
it in next year's "Top Projects of 2004."
Sheila Bacon, Editor
Northwest Construction
magazine
1.) OHSU
Patient Care Facility, Portland, Ore.
Construction cost: $120,000,000
General contractor: Hoffman/Andersen
Joint Venture, Portland, Ore.
 |
|
OHSU Patient Care Facility sitework, Portland, Ore.
Photo courtesy of Hoffman
|
When completed in 2005, this new 300,000-sq.-ft. patient
care center will provide comprehensive health care for the
region, incorporating more than 100 new inpatient beds; state-of-the-art
surgical suites and intensive care facilities; and two outpatient
clinics (the OHSU Cancer Institute and the OHSU Center for
Women’s Health). The facility’s built-in technologies will
enable caregivers to offer advanced care and to ensure safety
standards among the most rigorous in the nation.
The 11-story building features skybridge connections with
OHSU Hospital and a four-level, 456-space parking garage;
built under S.W. Campus Drive – one of only two roads into
and out of campus.
The project’s design also includes a public aerial tram that
will connect the OHSU campus to the developing South Waterfront
district. The tram’s terminus will be located at the Patient
Care Facility.
2.) Bridgeport Village, Tualatin, Ore.
Construction cost: $80 million
General contractor: Opus Northwest,
Portland, Ore.
Construction of the $80 million Bridgeport Village will bring
a number of upscale retailers to Tualatin, including Oregon’s
first Crate & Barrel, Wild Oats Market, PF Chang’s, Coldwater
Creek and other specialty merchants. Located just off Interstate
5, the retail development will also feature office space and
a 20-screen cinema.
When completed in the summer of 2005, Bridgeport Village
will also offer 200,000 to 300,000 sq. ft. of Class A office
space.
The open air-style development features extensive landscaping
and a main street appeal.
In collaboration with Washington County, the Oregon Department
of Transportation, City of Tualatin and City of Tigard, Opus
has plans for major improvements to the Interstate 5 and Lower
Boones Ferry intersection, SW72nd Ave. and Bridgeport Road.
3.) Rogue Valley Medical Center expansion
and renovation, Medford, Ore.
Construction cost: $76,000,000
General contractor: DPR Inc.,
Redwood City, Calif.
Considerable foresight on the part of the project team has
resulted in a smooth expansion and renovation project at Rogue
Valley Medical Center.
A full-scale mock-up of a typical patient room and toilet/shower
area was built a year before construction on patient rooms
began, allowing doctors, staff and visitors to offer comments
and suggestions. Those comments were incorporated into the
final design, eliminating the potential for costly change
orders in the future.
A goal of the owner to use local businesses in the medical
center’s construction resulted in the use of local businesses
for approximately 70 percent the job’s first phase. DPR created
a 4D CADD presentation of the scope of work and DPR’s approach,
then actively solicited local subs during the bidding process.
The job involves a 250,000-sq.-ft. steel-framed addition
and an 80,000-sq.-ft. renovation of existing facilities. New
construction includes a four-level bedtower over a two-story
base containing a new emergency department, expanded surgery
center, new kitchen and dietary department and renovated imaging
and diagnostics departments. The project also includes a 632-stall,
four-level post-tensioned parking garage, a new two-level
cast-in-place helicopter landing pad structure, and extensive
utilities relocation and site development.
Construction completion is scheduled for July 2005.
4.) OHSU Biomedical Research Facility,
Portland, Ore.
Construction cost: $70,000,000
General contractor: Hoffman/Andersen
Joint Venture
This 265,000-sq.-ft. building is key to implementing the
“Oregon Opportunity,” a public/private initiative intended
to assist Oregon Health and Science University in becoming
one of the country’s leading centers for biomedical research.
The building will provide state-of-the-art wet research labs
and associated support, conference areas, an expanded vivarium
(animal research area), and potentially, the OHSU Center for
Advanced Imaging.
The siting scheme reinforces the notion of a “necklace” of
interconnected research buildings, with the Basic Sciences
Building to the west, continuing to the Vollum Institute,
the Medical Research Building, and finally, this project.
The concept also establishes a new courtyard as a major entry
to the North Campus research project.
The facility will include seven stories above an entry courtyard.
New vivarium space will be located below grade and connected
to the existing vivarium in the Medical Research Building.
The imaging center is planned for the courtyard level to facilitate
connections to the outpatient clinic.
The estimated completion date is June of 2005.
5.) New Columbia HOPE VI Redevelopment,
Phase I, Portland, Ore.
Construction cost: $59,000,000
General contractor: Walsh Construction
Co., Portland, Ore.
The New Columbia project is located on 80 acres bordered
by Columbia Boulevard. North Adriatic and North Houghton streets
in Portland. The original community of affordable housing
– Columbia Villa – was built in the 1940s to house wartime
shipyard workers. It has now been cleared for a new affordable
housing community with apartments, owner-occupied homes, parks
and commercial space.
The demolition and abatement portions of the redevelopment
include abatement and removal of 193 housing structures and
nine community buildings. All structure foundations, sidewalks
outside of the existing street rights-of-way, and above-ground
sitework features have been demolished, and all underground
utilities at the removed structures have been decommissioned.
At the end of this portion of work, the asphalt pavement and
adjacent sidewalks will be the only visible remnants from
the original Columbia Villa development.
6.) Elizabeth Lofts, Portland, Ore.
Construction cost: $38,900,000
General contractor: Howard
S. Wright Construction Co., Portland, Ore.
 |
|
Elizabeth Lofts, Portland, Ore.
Image courtesy of HSWCC
|
Howard S. Wright Construction Co. is currently building The
Elizabeth an downtown Portland – a mixed-use development housing
182 residential units, retail space and a parking garage on
half a city block.
The 372,571-sq.-ft., 16-story building features 13,704 sq.
ft. of retail space on the ground floor. The parking structure
–one level underground and two above – will accommodate more
than 200 vehicles.
The structure’s exterior skin is brick with precast features
and extensive ornamental metal detailing. The building incorporates
a custom window system with extensive glass and large curtainwall
bay windows. Floors four through 14 feature terraces with
views of the North Park Blocks and the Willamette River bridges.
The penthouses feature two-story living areas and fireplaces.
The northwest corner of the block will feature an exterior
common area and restaurant for residents and retail shoppers.
7.) Newberg
Replacement Hospital, Newberg, Ore
Construction cost:$37,000,000
General contractor: Skanska
USA Building, Beaverton, Ore.
The Providence Newberg Replacement Hospital is a 143,500-sq.-ft.
hospital with an attached 6,500-sq.-ft. medical office building.
Built on a greenfield site, the new structure will replace
the existing Newberg hospital about a mile away.
The medical center will double in size and the emergency
room will expand from seven to 14 beds. MRI, which is now
provided in a mobile unit three days a week, will move in-house
and be available 24 hours a day. Inpatient beds will increase
from 35 to 45 beds. The building will also include clinic
space, X-ray rooms and exam/treatment facilities.
The project’s exterior is brick veneer and metal panels.
The project started last June, and construction completion
is expected in November 2005.
8.) Pinnacle Lofts and Condominiums,
Portland, Ore.
Construction cost: $35,000,000
General contractor: Andersen
Construction Co., Portland, Ore.
The Pinnacle Condominiums, located at
the corner of 9th and Naito Parkway in Portland, is an “L”
shaped building with 176 units over two levels of underground
parking with 205 stalls.
The building includes a seven story loft wing and a 14 story
finish wing. The loft units will boast 10-ft.-high concrete
ceilings with exposed utilities. Finishes for both the loft
units and the tower units will include Cacao wood flooring
imported from Indonesia, maple cabinets and pre-stained birch
doors and hemlock base.
The unique exterior of the 326,000-sq.-ft. structure consists
of exposed slab edges at all floors. The brick is an Ironspot
oversized brick that will span from floor to floor. The unit
windows are oversized tilt and turn windows. The lobby tower
will feature glass curtain wall spanning from the ground floor
to the 14th floor, giving the main entrance the glowing appearance
of a lantern.
The main lobby includes a radius stairwell, stainless steel
handrails, buffalo stone flooring and wall tile.
9.) Oregon State University Kelly Engineering
Center, Corvallis, Ore.
Construction cost: $34,700,000
General contractor:
Skanska USA Building, Beaverton, Ore.
Featuring sustainable “green” design elements, this new 146,000-sq.-ft.
building will include wireless classrooms, flexible learning
labs, office clusters, commons areas and a centrally located
café. The building will provide space for more than 360 professors
and graduate students.
Located on the north side of campus, the project is part
of the engineering department’s goal to attract quality faculty
and graduate students and expand the program.
One side of the building is three stories and the other four,
with a full height atrium down the middle. Raised access flooring
throughout the building will keep most of the mechanical systems,
voice and data cabling and electrical systems underfoot, allowing
for more flexible use of floor space.
The cast-in-pace, post-tensioned concrete building is clad
in brick, metal paneling, precast concrete and glass curtainwall.
It will seek a Gold LEED rating from the U.S. Green Building
Council upon completion.
Sustainable elements include a rainwater recovery system,
a natural ventilation system, the use of low VOC products.
Ninety percent of jobsite waste is recycled or reused, and
building materials are procured regionally. Before the completed
building is occupied, it will receive a two-week flush to
eliminate odors, off-gasses and other contaminants.
10.) Brewery Block 5 – South Pearl Apartments,
Portland, Ore.
Construction cost: $33,805,000
General contractor: Hoffman
Construction Co., Portland, Ore.
This 16-story mixed-use apartment tower is being built on
top of a previously completed underground parking structure,
which will continue to operate throughout the project. The
tower will include a three-story base encompassing ground-level
retail and second-story townhouses that will be accessed from
an elevated courtyard. This “podium,” clad in precast concrete
panels, is designed to maintain the established streetwall,
anchor the building, and provide a comfortable pedestrian
scale at the sidewalk. The tower façade is wrapped in a sleek
glassy skin with a south-facing concrete grid that provides
both balcony areas for residents as well as effective solar
control.
Similar to adjacent Brewery Block construction, the building
will achieve LEED certification. Construction continues to
occur in the midst of a busy retail-residential Pearl District
neighborhood.
11.) Lake Oswego High School,
Lake Oswego, Ore.
Construction cost: $31,870,000
General contractor:
Robinson Construction, Hillsboro, Ore.
12.)Interstate 5 McKenzie and
Willamette Detour Bridges, Eugene, Ore.
Construction cost: $28,900,000
General contractor: Hamilton
Construction Co., Springfield, Ore.
13.) The Tower and Garage at Station
Place, Portland, Ore.
Construction cost: $27,300,000
General contractor: Andersen
Construction Co., Portland, Ore.
14.) Lakeridge High School, Lake Oswego,
Ore.
Construction cost: $25,000,000
General contractor: Hoffman
Construction Co.
15.) The Avenue Lofts, Portland,
Ore.
Construction cost: $24,500,000
General contractor: Howard
S. Wright Construction Co., Portland, Ore.
16.) Broadway Housing at Portland
State University, Portland
Construction cost: $24,300,000
General contractor: Hoffman
Construction Co.
17.) (TIE) The Burlington, Portland,
Ore.
Construction cost: $22,000,000
General contractor: Hoffman
Construction Co.
#17 (TIE) Salem Conference Center and
Parking Garage, Salem, Ore.
Construction cost: $22,000,000
General contractor: Rushforth
Construction Co., Tacoma, Wash.
19.) 1620 Broadway, Portland,
Ore.
Construction cost: $18,000,000
General contractor: Swinerton
Builders
20.) Newberg High School Upgrade and
Addition, Newberg, Ore.
Construction cost: $17,884,140
General contractor: Emerick
Construction
2003 Top Projects WASHINGTON
1.) Safeway Distribution Center, Auburn,
Wash.
Construction cost: $95,000,000
General contractor: Turner
Construction Co., Seattle, Wash.
Once the massive Safeway Distribution Center is completed
in April 2005, it will include nine structures on 116 acres
for a total of nearly 1.2 million sq. ft.
The grocery warehouse and refrigeration warehouse are the
two largest structures in the complex, each totaling more
than 500,000 sq. ft. The grocery warehouse is a 50-ft. clear
height structure with 50-ft. by 40-ft. bays, featuring tilt-up
construction, steel joist and beam roof, and metal deck with
three-ply insulated roofing. The refrigeration warehouse features
similar construction materials, and is divided into three
sections: frozen foods, meat and eggs, and perishables.
Other structures include a 31,000-sq.-ft. recycling center,
1 20,000-sq.-ft. truck maintenance center, an administration
building, fueling station, two guard houses and two pump houses.
The site features a self-contained storm system with six
oil-water separators that discharge into a four-acre, two
cell holding pond with an 8.6 million gallon capacity.
2.) High Point Redevelopment,
Seattle, Wash.
Construction cost: $65,000,000
General contractor: Absher Construction
Co., Puyallup, Wash.
 |
|
Cutline: High Point Redevelopment, Seattle, Wash.
Photo by SkyPix
|
The first phase of the Seattle Housing Authority’s redevelopment
of the High Point public housing community in West Seattle
includes new infrastructure and construction of 344 rental
units. Private builders will add another 350 units in phase
I.
Redevelopment will remove all existing housing, roads and
utilities, and replace them with new infrastructure, housing
and community facilities on the 120 acre property. The two
redevelopment phases together will create a mixed-income community
of 1,600 units of rental and for-sale housing.
The project ensures that current High Point residents are
able to return to the neighborhood once construction is complete.
The renovated neighborhood’s new street grid will reintegrate
High Point with the rest of West Seattle, eliminating the
former meandering street pattern that disconnected High Point
from surrounding neighborhoods. a network of parks and green
streets will connect the varied areas within the community,
and provide recreational opportunities.
High Point is the largest of the Seattle Housing Authority’s
three major family housing revitalization projects. The second
phase of the project will be built between 2006 and 2009 under
another contract.
3.) Cristalla Condominiums, Seattle,
Wash.
Construction cost: $60,000,000
General contractor: Cristalla
Owner/Builder
This new residential tower in downtown Seattle features 197
units on 17 floors and views of Puget Sound, the city and
the Space Needle.
The 425,000-sq.-ft. structure also features two ground floor
retail locations.
The units feature slab granite countertops in the kitchen
and porcelain tile and optional glass accents in the bathrooms.
Hardwood floors are used throughout the living areas in the
residences, and translucent sliding doors in most units let
light in, yet provide privacy.
Cristalla also features a 24 hour concierge, an exercise/weight
room, dry and steam saunas, a whirlpool spa, a dog area on
the Sky Terrace, and controlled/monitored parking. Unit prices
range from $160,000 to more than $3 million.
Completion is scheduled for late spring of 2005.
4.) Mt. Tahoma High School, Tacoma,
Wash.
Construction cost: $56,500,000
General contractor: Lease Crutcher
Lewis, Seattle, Wash.
The Mount Tahoma High School project will replace an
existing outdated high school on a 90-acre site in the south
end of Tacoma. Driven by the educational program, this Gates
Grant school is designed to be flexible for curriculum changes
and community use, to accommodate a variety of teaching and
learning styles, and be expandable for growth. The programmatic
components of this comprehensive, state-of-the-art high school
are organized to facilitate community use and access; create
a centralized social “heart”; maximize daylighting; celebrate
the view of Mount Rainier (Mt. Tahoma) and personalize the
learning environment by creating “interdisciplinary learning
communities”.
The 270,000-sq.-ft.
facility accommodates 1,800 students and features two general
curriculum wings, a 3,100-seat stadium, two gymnasiums, a
competition swimming pool and a 400-seat auditorium. The auditorium
has two seating areas which rotate to become separate lecture
halls.
5.) FY03 Whole Barracks Renewal, Fort
Lewis, Wash.
Construction cost: $41,500,000
General contractor: Skanska
USA, Seattle, Wash.
The FY03 Whole Barracks Renewal project at Fort Lewis consists
of construction of six, three story barracks and two soldier
community buildings with living/sleeping rooms and semi-private
baths to house a total of 500 soldiers. The project also
encompasses the medium company operations facilities, a large
battalion headquarters with a classroom, maintenance storage
facilities and all associated sitework and utilities.
6.) Bremerton Harborside Kitsap Conference
Center, Bremerton, Wash.
Construction cost:
$40,000,000
General contractor: Opus
Northwest, Bellevue, Wash.
 |
|
Bremerton
Harborside Kitsap Conference Center, Bremerton, Wash.
Image courtesy
of Opus NW
|
Bremerton Harborside
is a new $40 million public/private venture between Opus Northwest
and the City of Bremerton. Set on the southern waterfront
of Bremerton, this new mixed-use project will become the rejuvenated
heart of Kitsap County.
The project will be a highly visible urban mixed-use development
adjacent to the Bremerton ferry terminal. The downtown
revitalization project will include a conference center, offices,
retail space, hotel, parking, restaurant and marina harbormaster
facilities. The conference center will bring public
and private interests together at the heart of the city -
its waterfront.
A unique aspect
to the project is its Wet Design water feature climbing up
from the steps of the marina, to the top of the plaza and
into the heart of the mixed-use center. The installation will
feature choreographed music and a water show, spraying jets
of water 50 ft. into the air.
Bremerton Harborside
tenants include the City of Bremerton, Port of Bremerton,
Hilton Hampton Inn (Bremerton’s first downtown waterfront
hotel), Kitsap Transit, Cold Stone Creamery and Subway Sandwiches.
Completion of the project is scheduled for this fall.
7.) Wal Mart Distribution Center,
Grandview, Wash.
Construction cost: $39,164,153
General contractor: JE Dunn
Northwest, Portland, Ore.
The 859,520 sq. ft. Wal Mart Distribution Center sits on
110 acres in Grandview, Wash. The project includes 370,000
sq. ft. of freezer space, separated for storage of ice cream,
meat and poultry, deli and dairy, wet produce and dry produce.
Each freezer/refrigerated area has different requirements
and specifications. The project also features 466,000 sq.
ft. of dry, non-refrigerated storage space. The remaining
space houses maintenance staff and workspace; office space
and equipment; and fuel dispensing operations.
The buildings are pre-engineered metal structures on concrete
foundations and stem walls.
The entire complex was completed on a fast-track, 10-month
schedule. The job had an onsite batch plant and crews working
24 hours a day, seven days a week in temperatures averaging
100 degrees or above.
8.) Northwest Detention Center,
Tacoma, Wash.
Construction cost: $38,500,000
General contractor: Lydig Construction,
bellevue office
Located in a heavy industrial area near the Port of Tacoma,
this new detention facility includes a processing area, medical
and dental facilities, courtrooms, interview and visitation
areas and food prep and laundry facilities. When in full operation,
the complex will include 800 beds in four housing pods and
a fifth area dedicated to administration and support services.
The project is being constructed on an aggressive schedule
with a timeline of just over 10 months.
9.) Rainier Vista HOPE VI, Seattle
Construction cost: $37,549,682
General contractor: Walsh Construction,
Seattle
The Rainier Vista project is located in southeast Seattle.
Originally a 481-unit World War II-era garden community, the
38-acre site has now been cleared for a vibrant new mixed-income
community. Residents have participated in site-design meetings
and assisted in the selection of architects, security services,
the senior and disabled housing partners, and the relocation
counselor.
Rainier Vista’s 1,010 units of new housing will help meet
current affordable housing needs in the Seattle area. Walsh
Construction’s role includes demolition, infrastructure, right-of-way
landscaping, and new construction of 410 low-income housing
units. The low-income housing includes 22 units for people
with disabilities and 78 units for the elderly, 75 of which
will be in two, four-story buildings with elevators.
Rainier Vista will also feature 100 work-force housing units,
200 for-sale homes for low-income working families, and 300
homes for sale to the general public. Additional plan components
include parks and community gardens. Community space to house
existing and new social services will be located onsite to
meet residents’ needs.
Phase I is scheduled for completion in summer 2005.
10.) Auburn High School, Auburn,
Wash.
Construction cost: $35,6000,000
General contractor: Absher Construction
Co., Puyallup, Wash.
The Auburn School District’s new High School No. 4 will be
an airy, spacious facility, organized around a central student
commons flanked by two wings when completed in 2005. An administrative
and academic wing will be located to the south, and an activities
and technology wing to the north.
The facility’s H-shaped plan is intended to maximize natural
lighting into as many educational spaces as possible. In addition,
the H-shape will provide students and staff with a smaller,
more comfortable sense of scale. Rather than relying on a
large, block-like centralized facility, this building design
will allow for simple, gabled roofs over the majority of the
buildings. The main entrance of the school will be centered
on the south façade, with architectural elements that create
a spacious and welcoming impression.
The two-story brick building is being built on a 40-acre
site, and will accommodate 1,500 students. When finished,
the new high school will be 195,000 sq. ft. and include 31
general classrooms, six computer labs, a career center, a
400 seat auditorium, a 600 seat cafeteria with a full-service
kitchen, main and auxiliary gymnasiums, a field house, a green
house, and several sports fields and tennis courts.
The project was designed by BLRB Architects of Tacoma.
11.) 23rd and Madison Mixed Use
Project
Construction cost: $32,000,000
General contractor: Cressey
Development, Seattle, Wash.
12.) Bonney Lake High School,
Bonney Lake, Wash.
Construction cost: $29,100,000
General contractor: Garco Construction,
Spokane, Wash.
13.) 9th and Stewart Life Sciences
Building, Seattle
Construction cost: $27,300,000
General contractor: Lease Crutcher
Lewis, Seattle, Wash.
14.) Gonzaga University Arena,
Spokane, Wash.
Construction cost: $27,000,000
General contractor: Garco Construction,
Spokane, Wash.
19.) Bethel High School, Graham,
Wash.
Construction cost: $26,947,941
General contractor: Wick Constructors,
Seattle, Wash.
16.) City of Seattle Police Support
Facility, Seattle
Construction cost: $24,500,000
General contractor: Turner Construction
Co., Seattle
17.) BP Cherry Point Refinery
ISOM Project, Blaine, Wash.
Construction cost: $24,000,000
General contractor: JH Kelly,
Longview, Wash.
18.) Ellensburg High School, Ellensburg,
Wash.
Construction cost: $22,296,500
General contractor: Lydig Construction,
Spokane, Wash.
19.) Madison
Middle School, Seattle
Construction cost: $22,200,000
General contractor: Garco Construction,
Spokane, Wash.
20.) Combined Arms Collective
Training Facility, Fort Lewis, Wash.
Construction cost: $21,978,225
General contractor: Pease Construction,
Lakewood, Wash.
|